The first meeting of the Community Reference Group was held at the Bemm River Community Centre on Wednesday 19 August 2009.  Those present were ;

John Groom : Chairperson
Lara Caplygin : Project Manager
Pam Knight : Project Assistant

and the community representatives of

Don Cunningham
Len Luffus
Christina Foster
Russel Francis
James McIntyre
David Sturgess
Lindsay Williams

Several options were discussed for the re-use of effluent and the funding of the project was discussed.  A rough estimate of the cost was given at $M 2,2 and funding from the government of $K 870 has been granted.  Of the remaining EG Water is likely to put in about $K 870 leaving the rate payers with the remaining costs.  The Council would be charged for the Caravan Park and the Community Centre.

 

If you want to have an input, contact a member of the committee who will put forward your views.